Fitout

University Of Technology Sydney

Client
Architect
Foran Design
Location
Sydney
Budget
$300,000
Time
5 weeks

Trinity delivered the project across a 5-week program with the users moving their equipment in to their new defect-free space as programmed. This project work involved re-purposing an existing under-utilised part of the science faculty to form a purpose-built optics research lab. The space was small and the technical requirements of the optics lab were very specific.

Scope of Work

AC stability within 1-2 degrees

Compressed air outlets

Reticulated nitrogen to each work station

HEPA filters on all AC outlets

100% elimination of natural light

Laser Interlock

New flooring, furniture, electrical, data and lighting