National Parks and Wildlife Services Depot




Department of Planning & Environment
Bokor Architecture & Interiors
Mundamia
53 weeks
Our team successfully executed the construction of a new office building for the National Parks and Wildlife Services (NPWS) Depot. The project was delivered in several stages. Initially, the preliminary stage entailed the demolition of existing structures to prepare the site for construction. Moving into Construction Stage 1, efforts focused on erecting a new 390sqm depot, complete with offices and breakout areas, alongside the refurbishment of existing storerooms to optimise their functionality. Subsequently, in Construction Stage 2, attention turned to the creation of a new car park and the implementation of associated stormwater drainage systems, crucial for supporting the operational requirements of the facility. Through meticulous planning and execution, our team delivered a comprehensive solution tailored to the requirements of the NPWS.